Town of Chatham Collection System Construction Project
Welcome Areas of Work Public Notices Schedule Information Contact
Links
Town of Chatham Website
Frequently Asked Questions (FAQ)
Comprehensive Management Plan
Chatham Water & Sewer
Chatham DPW
Chatham Health & Environment
Town of Chatham Website
Boston Smartraveler.com
Chatham Businesses
Areas of Work
Areas of Work
Click here to enlarge the map above.
Areas of Work

Pumping Station construction is planned at the following locations:

  • Pumping Station 37 – Lime Hill Road – located off of Main Street / Route 28 west of the Lime Hill Road intersection
  • Pumping Station 43 – Meadow View Road – located at the intersection of Meadow View Road and Vineyard Avenue
  • Pumping Station 44 - Barn Hill Road – located at the intersection
    of Barn Hill Road and Hardings Beach Road
  • Pumping Station 50 – George Ryder Road – located behind the Town’s animal control building
  • Pumping Station 51 – Huckleberry Road – located south of the existing Water Pollution Control Facility
  • Horseshoe Lane – grinder pump – located at the end of
    Horseshoe Lane

Collection System construction is planned along the following roads.   Sewers at this time may not extend the entire length of these roads, please visit the link to the maps showing the locations.

Gravity Sewer Roads

Completed areas still may require site restoration and cleanup or addressing outstanding items.

  • George Ryder Road – approximately from the Airport south to
    Route 28/Main Street (completed)
  • Barn Hill Road – from Route 28/Main Street south to Barn Hill Lane (completed)
  • Meadow View Road – from Barn Hill Road to Vineyard Avenue (completed)
  • Meadow View Road South (completed)
  • Meadow View Road Extension (completed)
  • Horseshoe Lane – service to the Town grinder pump station (completed)
  • Vineyard Avenue – from Route 28/Main Street south towards Meadow View Road (completed)
  • Route 28/Main Street – from Beacon Hill to Sam Ryder (completed)
  • Route 28/Main Street – from Sam Ryder to Joshua's Way (paved, awaiting final site cleanup)
  • Route 28/Main Street – from Crosby Lane to George Ryder Road (paved awaiting final site cleanup)
  • Route 28/Main Street – from George Ryder to Barnhill Road (completed)
  • Route 28/Main Street – from Barnhill Road to Old Queen Anne (in progress)
  • Route 28/Main Street – from Old Queen Anne to Crowell Road (Five Corners) (completed)
  • Crowell Road Intersection - from Queen Anne to Oyster Pond Furlong (installed, awating final connection and final paving)
  • Sam Ryder Road (completed)

Low Pressure Sewer Roads

  • Barn Hill Road – Barn Hill Lane to town landing (completed)
  • Summer Hill Lane (completed)
  • Marcus Lane (completed)
  • Plum Daffy Lane (completed)
  • Route 28/Main Street - from Joshua’s Way to Crosby Lane (paved awaiting final site cleanup)
  • Whiteley’s Way (paved awaiting final site cleanup)
  • Horseshoe Lane (from grinder pump station to Meadow View Road) (completed)