Schedule

Last updated on  

During construction this page will provide estimated time of construction (these will be updated periodically – locations are approximate based on nearest cross street). The Route 28 overall construction schedule is currently proposed to extend from March 2010 until September 2013.

Please visit our listing of Chatham Businesses, for more information on their location, hours of operation. Requests to add Chatham business can be sent to the Town or the Project Manager listed on our Contact's Page.

 

FALL 2011
PUMPING STATIONS

 



 

Fall 2011 Complete

The proposed map of the upcoming schedule as presented to the Selectmen August 16, 2011 can be found here (for the construction schedule map showing active detours, see map and link below):

Upcoming Construction:

Spring 2012- Sewer Construction - Date TBD

Dates are subject to change depending on construction progress and weather conditions.  Contractor hours are from 7 am to 7 pm, as approved at the August 16, 2011 Selectmen's meeting. No work is scheduled for nights (after 7 pm), weekends, or holidays.

Up to 2 Detours may be in effect at any one time. Contractor may work in other areas as long as one lane of alternating traffic is maintained. 

Route 28/Main Street Construction Areas (West to East)

DETOURS IN EFFECT WILL BE IN SHOWN RED
(work in other non-highlighted zones may continue for site cleanup and restoration)

When detours are in effect Route 28 will be closed to thru traffic, however, the road will be open to Local Business Traffic and Residents.  Please see construction signs as access to/from local businesses and side streets within the detour will be construction dependant and may Change during construction.  Work may continue in these areas even if not shown in red, and will be done without the detour as stated above.

Route 28 Detours Detour 1 (Route 137 to Middle Road to Sam Ryder Rd.) Detour 2 (Sam Ryder to Old Queen Anne to George Ryder) Detour 3 (George Ryder to Old Queen Anne) Detour 4A (Old Queen Anne to Stepping Stones to Heritage Ln) Detour 4B (Crowell Road to Stepping Stones Hertage Ln) Click on the Detours shown on the Map above to go to the related detour area for detour and construction schedule information. For Project areas outside of the Route 28 detours, please click here.

Detour 1 (Route 137 to Middle Road to Sam Ryder Rd.)

View Map of Detour 1
Route 28 between Route 137 and Sam Ryder Road

Sewer construction completed.

 

Detour 2 (Sam Ryder to George Ryder)

View Map of Detour 2
Route 28 between Sam Ryder Road and George Ryder Road

Sewer construction completed.

Detour 3 (George Ryder to Old Queen Anne)   

View Map of Detour 3
Route 28 between George Ryder Road and Old Queen Anne

 

Final paving and site restoration will be completed in Spring 2012.

Detour 4 (Old Queen Anne to Stepping Stones to Crowell Road)

View Map of Detour 4
Route 28 between Old Queen Anne and Crowell Road

Sewer construction completed between Linden Tree Lane and Snow Lane.

Detour 4A (Old Queen Anne to Stepping Stones to Heritage Ln)

View Map of Detour 4A
Route 28 between Old Queen Anne and Heritage Lane

Sewer construction completed between Linden Tree Lane and Heritage Lane.

Detour 4B (Crowell Road to Stepping Stones Hertage Ln)

View Map of Detour 4B
Route 28 between Heritage Lane and Crowell Road Intersection

Sewer construction completed between Linden Tree Lane and Heritage Lane.

Route 28 Crowell Road Intersection and Queen Anne to Oyster Pond Furlong

Please see Public Notice

Town Road Construction Areas (West to East)
Barnhill Road

Sewer construction completed. Work remains at pumping station site. 

Town is continuing to work on the paving and sidewalk project, which is outside the sewer project.

Meadowview Neighborhood (Meadowview, Meadowview South, Horseshoe, Meadowview Extension)
Sewer construction completed. Work remains at pumping station site. 

 


 

Pumping Stations (Contact 2)
Work continues thru Spring 2012
Huckleberry Road PS 51
Work continues thru Spring 2012
George Ryder Road PS 50
Work continues thru Spring 2012
Barn Hill Road PS 44
Work continues thru Spring 2012
Horseshoe Lane Grinder Pump
Work continues thru Spring 2012
Meadow View Road PS 43
Work continues thru Spring 2012
Lime Hill Road PS 37

 